PROGRESS
OF CONSTRUCTION
|
|
| BANGALORE
(Yelahanka-A) |
|
366
Dwelling units are being planned in the 50 acres of land acquired
at Bangalore Yelahanka Part 'A as under: -The project is being
planned in a Single Phase as under: -
|
SNO.
|
TYPE
OF DWELLING UNITS |
Nos
|
|
(a)
|
Duplex
Single Unit 400 sq yds plot (incremental on first floor) |
207
|
|
(b)
|
Duplex
Single Units in 300 sq yds plot (incremental on first
floor) |
111
|
|
(c)
|
Economy
Apartments (G+1) |
32
|
|
(d)
|
Thrifty
Apartments (G+1) |
16
|
Environment
Impact Assessment Report has been submitted to Ministry of
Environment and Forests. A Presentation has been held. Observations
raised by the Environment Assessment Committee have been clarified.
Formal approval is awaited.
|
|
| BANGALORE
(Yelahanka-B) |
|
Planning of Dwelling Units in 11 acres of plot is being undertaken.
|
|
| Greater
Noida Phase-III |
|
Construction work for nearly 1200 balance Dwelling Units is
expected to start in mid 2007. With the restriction on height
of buildings being removed by Greater Noida Authority, it
is proposed to increase the height of various towers. This
will increase not only the total number of Dwelling Units
but also the areas of open greens
|
|
| JAIPUR
Phase V |
|
88
Dwelling Units (Economy) have been planned in this phase.
Construction work is likely to commence by mid 2007.
|
|
|
Nainital (Khurpatal) |
|
The Nainital Lake Development Authority has approved the plans
for the scheme. Preparation of working drawings is in progress.
Scheme is open for allotment of second dwelling unit also.
138 applications have been received against planned construction
of 81 dwelling units.
|
|
|
Panchkula, Sector 27 |
|
HUDA has allotted 12.65 acres of land. 483 DUs are being
constructed. Planning has been completed. Tender action is
in hand. Booking letters have already been sent to the allottees
|
|
| Silver
Sand Island KOCHI |
|
Silver
Sand Island, Kochi: Duplex Single Dwelling units are being
planned. The response to the project has been very good. Selection
of architect has been done. Planning process is in hand.
|
|
| Army
College of Nursing Jalandhar |
|
AWHO has been entrusted with the construction of Army College
of Nursing at Jalandhar. The planning for the same is in progress.
The construction is planned to commence by early 2007.
|
|
|
Bhubaneshwar Phase II |
|
36 Economy Apartments have been planned. Response to the project
has been good. Construction work has commenced in Aug 2006
|
|
|
GOA(PANAJI) |
|
The project is being planned in a Single Phase as under: -
|
SNO.
|
TYPE
OF DWELLING UNITS |
TOTAL
|
APPLICATION
RECEIVED
|
|
(a)
|
Duplex
Single Unit (Incremental on First Floor) |
8
|
15
|
|
(b)
|
Economy
Apartments (G+1) |
48
|
100
|
|
(c)
|
Economy
Apartments (G+2) |
36
|
|
(d)
|
Utility
Apartments (G+1) |
18
|
29
|
|
(e)
|
Thrifty
Apartments (G+1) |
18
|
29
|
Tender
action is in hand
|
|
|
Greater Noida Phase-1. |
|
Construction of 844 Dwelling Units is progressing satisfactorily.
Progress is nearly 80%. Work for external development is in
progress. Sample Dwelling Units are ready and are being visited
by allottees.
|
|
| Greater
Noida Phase-II. |
|
. Work on pile foundations for 784 Luxury and Super Deluxe
Dwelling Units is under progress.
|
|
| Gurgaon-
Sector 49 |
|
Construction work is progressing satisfactorily as per schedule
with the present progress being approx 40%.
|
|
|
Jai Jawan Awas Yojna-1 (Jaipur) |
|
As per directions of COAS, low cost housing schemes are
to be planned for serving JCOs/OR in all popular stations.
The pilot project has been undertaken at Jaipur where land
was already available with AWHO. 84 Dwelling Units are under
construction under Jai Jawan Awas Yojna-1. The progress of
work is satisfactory and as per schedule. All planned Jai
Jawan Apartments have already been booked. A long waiting
list exists for allotment against cancellation/surrender.
|
|
|
Jai Jawan Awas Yojna-2 (Jaipur) |
|
The second project under the scheme, Jai Jawan Awas Yojna-2
has also been planned in Jaipur. All 84 planned Dwelling Units
have been booked. Construction work has already commenced
in Dec 2006
|
|
|
Jaipur (Phase IV): |
|
20 Economy Apartments have been planned in this phase. The
construction work is in progress. The progress of work is
approx 69%.
|
|
|
Kolkata (VIP Road): |
|
A total of 222 dwelling units are being constructed. Construction
work is going on. Likely date of completion of the project
is Aug 2007.
|
|
|
Lucknow Tyagi Vihar Phase-II. |
|
Work has commenced to construct 18 Duplex Single Units and
48 Special Economy Apartments. Basement parking is also being
provided below the Special Economy Apartment blocks
|
|
|
SECUNDERABAD (Ved Vihar Phase IV) |
|
270 Dwelling Units are being constructed in this phase (DA
60, EA 180 and UA 30). The progress of the work is approx
62%
|
|
|
Ludhiana (Dugri Road) |
|
Ludhiana (Dugri Road): Site is located near Sidwan Canal approx
4 Kms from Bus Stand. Construction of 170 Dwelling Units comprising
of Deluxe A, Deluxe B and Economy Apartments has commenced.
|
|
| Noida
Sector 82: |
|
|
1010
Dwelling Units and Central Facilities are under construction.
The progress of the work is behind schedule and efforts are
on to complete the work at the earliest.
|
|
|
Pune (Hadapsar). |
|
|
144 Dwelling Units in stilt +4 configuration (with lifts) are
under construction. Expected date of completion is Jun 2007.
Booking/allotment of the same is open for Army personnel only
against cancellation, as all Dwelling units are already booked.
|
|
|
Jai Jawan Awas Yojna, Pune: |
|
195 Jai Jawan Apartments have been planned. The Scheme has
been over subscribed. Annual Registration scheme on first
come first serve basis is still open. All new applicants are
being kept in the waiting list for allotment against cancellation/surrender.
Tender action for the project is in hand.
|
|
Panchkula (Sector 20) |
|
556 Dwelling Units along with Central Facilities are under
construction. The expected date of completion is May 2007.
|
|
Secunderabad (Ved Vihar Phase IV). |
|
270 Dwelling Units are being constructed in this phase (DA
60, EA 180 and UA 30). The progress of the work is approx
62%.
|
| Projects Completed
|
|
Belgaum.
|
|
All the 22 Single Unit Houses and four shops have been sold
in the colony. Annual registration is open for dwelling units
only against cancellation.
|
|
Bhubaneswar Phase-I. |
|
56 Single Units, 12 Economy Apartments and 6 Thrifty Apartments
have been constructed in Phase-I. All Dwelling Units except
one have been handed over. Most of the units have been occupied
and the campus is coming up nicely.
|
| Land
Procurement. |
|
Guwahati. |
|
3.3 acres of land have been allotted to AWHO by the state
Govt. at Narangi Cantt at Guwahati..
|
|
Allahabad. |
|
6.5 acres of land have been allotted to AWHO at Kalindipuram
at Allahabad.
|
|
Bathinda |
|
. 4.9 acres of land have been acquired at Village Bibiwala
for Jai Jawan Awas Yojna.
|
|
HOUSING LOAN FLEXI OR FIXED ?
Now a days all people who buy houses take housing loans to
partly finance the cost. Earlier most of AWHO allottees used
to hesitate in taking a loan and when they took it, it was
only as much as was absolutely necessary. They debated whether
to take a housing loan or not. Today the debate is whether
to take a loan at flexible (also termed floating or variable
by many agencies) or fixed interest rates.
Interest rates on housing loans have been fluctuating quite
a lot since last five years. The rates moved southwards so
much that from 13-14% they came down to 6.5-7.5%.This gave
boost to housing industry and the buyers began to opt for
bigger and bigger loans. But things began to change by 2005
when interest rates started moving up again.
With the latest round of increase in the interest rates
floating rates are now 9.5%-10.5% depending on the tenure
of loan. Taking Nov 2004 as reference point, EMIs have increased
by almost 25% on twenty five years loan from Rs. 790 per one
lakh to Rs 982 per lakh at present.
Earlier, loaning agencies used to increase the tenure of
repayment to keep the EMI unchanged. But now it may not be
possible in most cases because agencies do not want the repayment
period extending into retirement period. As a result loaning
agencies will have to increase the EMI. Only in case of very
young borrowers and very recent borrowers tenures may be increased
like in the past.
As the prime lending rate has increased, fixed rate of interest
has also increased. New rates will be applicable only to new
borrowers, unless the loaning agency had some conditions in
fine print.
Many borrowers are panicking due to so many hikes in the
floating interest rates. They are keen to switch to fixed
rate of interest for which 1.5-2% of loan amount will have
to be given as switch charges. Fixed rate of interest is likely
to be 11-11.25%. That means, in the first year loan will be
costing 13% per annum. Then onwards it will cost 11-11.25%
for entire term of loan, even if home loan interest rates
come down in the future.
Many bankers feel that chances of interest rates going up
by three percent are very remote. If interest rate goes up
to 13% then EMIs will increase by 20% from present level.
This will really lead to slowing down of construction activity.
The housing sector will definitely be adversely affected.
Therefore, many bankers are of the opinion that Home loan
interest rates have peaked. In medium to long term, they would
start declining to adjust with the global rates which are
much lower at around 6-8%. Those who shift to fixed rate now
will not be able to avail the benefit of any decline in the
rate of interest. Therefore it is felt that it would be better
for a borrower to stick to the floating/variable rate loan
scheme at the moment. In view of this opinion of the Bankers
it is advised that allottees before taking any loan discuss
this issue in detail with their loaning agencies.
|